Skip to content

Site Selection & Assessment

Aerial view of a commercial parking lot being surveyed for EV charging station installation with survey markers and desert rock formations in the background

Site Selection for EV Charging Stations

Choosing the right location is the foundation of a successful EV charging installation. This lesson covers the key factors in site assessment.

Tribal Land Consideration
Installing EV infrastructure on Fort Mojave trust land requires both tribal governance approval and BIA coordination. Begin the permit process early — BIA processing alone can take 60–120 days for simple permits.

Key Considerations

  • Electrical capacity: Assessing existing electrical infrastructure and available power. A Level 2 EVSE at 7.2 kW requires a 40A dedicated circuit; a DCFC at 50 kW requires a 200A+ service upgrade in many cases.
  • Accessibility: ADA/PROWAG compliance — accessible parking spaces must have an 8-foot adjacent access aisle and comply with surface grade requirements (max 2% in any direction). At least one accessible EVSE per facility is required for public chargers.
  • Demand analysis: Understanding current and projected EV adoption in the service area. Plan for at least a 5-year adoption horizon when sizing service entrance capacity.
  • Environmental factors: Weather protection, lighting, safety considerations. In the Mojave Desert, shade canopies are strongly recommended for both equipment longevity and user comfort.
Decision flowchart diagram for EV charging site assessment showing branching evaluation steps from location review through electrical capacity to final approval
Site assessment decision flowchart — follow each evaluation branch to determine site suitability.

Site Assessment Criteria — Quantitative Thresholds

Use this table to score candidate sites. A minimum threshold failure on any row requires corrective action or site re-evaluation before proceeding.

CriterionMinimum (Level 2 Only)Preferred (L2 + DCFC)Notes
Electrical service100A single-phase (Level 2 only)200A 3-phaseDCFC at 50 kW requires 200A+ service upgrade in most cases; verify with AHA-MACAV Power Service
Available panel capacity40A spare (one L2 circuit)100A+ spare or service upgradeEach 7.2 kW L2 requires a 40A dedicated circuit (NEC 625.22)
Accessible parking (ADA/PROWAG)1 van-accessible stall with 8-ft access aisle1 accessible stall per 4 EVSEAccess aisle must be ADA-compliant: max 2% cross-slope in any direction; firm, stable surface to charger
Cable reach to charge port15 ft (L2 minimum)25 ft (L2); 10–12 ft (DCFC)Measure from planned EVSE mount to vehicle charge port location at pull-forward position
Conduit run distance (panel to EVSE)Under 200 ftUnder 100 ftLonger runs require conductor upsizing for voltage drop; increases cost significantly
Shade / weather protectionRecommendedRequired for DCFCMojave Desert: 110°F+ summers. Shade canopies are required for DCFC equipment longevity and user comfort. Factor into construction cost.
Electrical Safety
Never assess electrical panel capacity without a qualified electrician. Verify all breaker ratings and conductor sizes before determining available capacity. Working in an energized panel without proper PPE and lockout/tagout procedures is a serious safety hazard.

Site Assessment Procedure

Conduct initial site survey
Walk the candidate site. Document parking layout, existing electrical infrastructure, lighting, and accessibility features. Photograph the electrical panel, service entrance, and proposed EVSE locations.
Score the site against threshold criteria
Use the quantitative thresholds table above. Any minimum threshold failure requires corrective action or site re-evaluation.
Assess electrical capacity
Have a qualified electrician verify panel capacity, service entrance rating, and available spare circuits. Document existing loads and calculate remaining capacity for EVSE.
Verify ADA/PROWAG compliance
Measure proposed accessible stall dimensions (8 ft wide + 8 ft access aisle for van-accessible). Check surface grade (max 2% slope) and accessible route to building entrance.
Submit for tribal and BIA review
Package site assessment with photos and scoring into a project concept document for tribal government approval and BIA permit application.

ADA/PROWAG Compliance

At least one accessible EVSE parking space is required for public chargers. Key requirements:

  • Stall dimensions: Accessible EV stall must be at least 8 feet wide with an adjacent 8-foot access aisle (van-accessible); 5-foot access aisle minimum for standard accessible stalls.
  • Accessible route: An unobstructed accessible route must connect the EVSE to the building entrance — free of curbs, slope obstacles, or surface hazards. The cable must not cross the accessible route when in use.
  • Surface grade: Maximum 2% slope in any direction within the accessible parking space and access aisle.
  • Reach range: EVSE controls and connectors must be within accessible reach range: 15–48 inches above ground for a forward approach; 9–54 inches for a side approach (per ADA Standards for Accessible Design §308).

Tribal Land Site Selection — BIA Permit Process

Installing EV infrastructure on Fort Mojave trust land involves both tribal governance and federal agency coordination. The typical workflow:

  1. Tribal government approval: Submit project concept to Fort Mojave Indian Tribe's planning/energy office. This is the first gate — BIA will not process permits without tribal government endorsement.
  2. BIA permit application: Submit a Right-of-Way or Permit to Enter application to the BIA Colorado River Agency (Needles, CA office). Required for any construction that permanently modifies trust land. Typical timeline: 60–120 days for simple permits; 6–12 months for complex ROW.
  3. THPO review: The Tribal Historic Preservation Officer (THPO) reviews for cultural resource impacts. Submit concurrently with BIA application — do not wait. THPO review adds 2–6 weeks.
  4. Tribal building authority permits: Fort Mojave has its own building permit authority for construction on trust land. Obtain tribal building permit after BIA and THPO clearance.
  5. Utility coordination: Contact AHA-MACAV Power Service for service upgrade or interconnection application. Submit early — utility interconnection can take 4–8 weeks independent of BIA permitting.

Note: On fee land within or adjacent to Fort Mojave, county (San Bernardino or Mohave County, AZ) permits may apply instead. Confirm land status with the Tribe's legal office before submitting any permit.

Tribal EVSE Success Stories
The Navajo Nation partnered with DOE and NEVI to install charging stations along US-491 and other corridors, navigating BIA trust land permitting at scale. Cherokee Nation deployed Level 2 EVSE at government buildings and health facilities starting 2022 using DOE Indian Energy grants — a model for tribal campus site selection.

Tribal EVSE Siting — Case Examples

Several tribal nations have successfully sited EVSE, providing useful precedent for Fort Mojave:

  • Fort Mojave Indian Tribe (AMPS): Currently deploying EVSE under CEC ARV-25-015, including tribal facility charging sites across the Fort Mojave campus. First-hand BIA permit experience being developed through this program.
  • Navajo Nation: Partnered with DOE and NEVI to install charging stations along US-491 and other corridors. Navigated BIA trust land permitting at scale; the Nation's energy division has published lessons learned accessible through DOE Indian Energy.
  • Cherokee Nation (Oklahoma): Deployed Level 2 EVSE at tribal government buildings and health facilities starting 2022. Used DOE Indian Energy grant funding and BIA technical assistance. Model for tribal campus site selection prioritizing community member access.
Additional Site Selection Resources & References

AFDC Site Assessment Guide: The Alternative Fuels Data Center provides a comprehensive guide for evaluating EV charging site suitability, including load analysis worksheets and ADA compliance checklists.

Joint Office Tribal Technical Assistance: Free technical assistance is available for tribal nations through the Joint Office of Energy and Transportation — including on-site assessment support for tribal land EVSE projects.

NEC 625 Site Requirements: Review NEC Article 625 for electrical requirements that affect site selection — particularly service entrance sizing (625.22) and outdoor GFCI requirements (625.54) that may require additional electrical work at candidate sites.

Loading...